Darwin LNG Dolphins Remediation

Client
Santos / ConocoPhillips
Construction site
Darwin, NT
Period
2020-2021
Market
Energy, Marine

KAEFER was engaged by ConocoPhillips for remediation works to structural steel on the berthing and mooring dolphins at the Darwin LNG (DLNG) Production Facility.

Client inspections had identified several locations for remediation due to coating breakdown and external corrosion on critical components. In addition to the dolphin structures, topside structural support members on walkways, fenders and other miscellaneous steelwork required remediation.

Our Scope
  • Supply & installation of a suitable access system (rope access)
  • Containment and collection of failed coatings
  • Surface preparation
  • Application of protective coatings

All works were required to be completed ‘online’ (LNG shipping operations continued throughout the project). KAEFER undertook detailed planning prior to works commencing, working in close collaboration with operational representatives from Santos / ConocoPhillips to determine shipping movements and schedule our works accordingly. The works schedule developed ensured minimal disturbance to facility’s ongoing operations and loading activities.

KAEFER Integrated Services
Delivering across full asset lifecycles, from construction to asset integrity, maintenance & shutdowns.
Contact us now +61 8 9224 4600

Further Case Studies