Project update at Olympic Dam

Tags:

Progress is well underway on the Flotation Integrity Project (FIP) at BHP’s Olympic Dam processing facility.

The project is all about upgrading Cleaner 1 – an ageing section of the flotation circuit – with new equipment and modern technology to support long-term operations.

So far, our teams have:

  • Completed major demolition works
  • Installed over 1,000m³ of new concrete foundations

What’s next? September marks the start of the main construction phase, with significant amounts of steel and piping arriving on site.

  • The erection of several large steel structures (~300 tonnes of steel, up to 20m high).
  • Installation of piping (~3.5km) servicing a range of fluids and connecting between the old plant and the new equipment.
  • Installation of mechanical items; including pumps, large sumps (up to 20 tonnes), large cells.
  • Installation of the electrical and instrumentation to accommodate the equipment.

It’s exciting to see the project taking shape as we move from foundations to major installations.

Count on us.

Latest News

Keep up to date with the latest from KAEFER in Australia