Olympic Dam SCM21 Shutdown

KAEFER was engaged as the primary contractor for access requirements and fabric maintenance on the shutdown.

KAEFER’s scope included

  • Civil works including demolition and replacement of slabs, pedestals and bund walls
  • Scaffolding – 1,220T of scaffolding was erected and dismantled
  • Insulation & cladding – 6,400m2 of insulation was removed and replaced
  • Surface protection – Remediation of 1,200m2
  • Rope access – >5,600 hours across mechanical, painting, and insulation scopes

In addition, due to the team’s high quality performance on the shutdown, KAEFER was engaged by Bechtel to complete additional mechanical scopes.