Olympic Dam BARS Project

KAEFER was engaged by BHP to provide installation services and Early Contractor Involvement (ECI) for the Bismuth & Antimony Removal Systems (BARS) Project at the Olympic Dam Mine in South Australia.

  • ECI – providing value through constructability and design reviews
  • Detailed earthworks
  • Concrete works including foundations, tank plinths, structural footings and ramp installation
  • Supply of FRP and stainless tanks, structural steel, FRP cPVC and stainless & carbon steel piping works, supply of pipe cladding
  • Installation of main piperack support structure, tanks and tank platforms including stairs, handrails and FRP grating
  • Installation of pipe & cable tray supporting structures and junction box
  • Installation of all steel, FRP and cPVC piping works, spanning instrument air, hydrochloric acid, portable water and steam lines (including tie-ins)
  • Installation of cooling towers for water and safety shower systems
  • Installation of the Beta package system, which separates acid from water to reduce acid consumption
  • Installation of LV switch room and all associated E&I works
  • Hydrotesting of all pipe and tank installations for plant commissioning
  • Assist in full plant commissioning for handover to production