KAEFER was engaged by Karara Mining to supply and install various equipment for the dewatering circuit at the Karara Mine.

Our Scope
  • Fabrication & installation of hoppers & cyclone overflow hoppers for 4 cyclone banks
  • Fabrication & installation of rubber-lined carbon steel pressure piping (DN600), including cyclone overflow, screen bypass, pumping suction piping & manifolds, underflow piping & discharge piping
  • Modifications to structural steel and installation of new structural steel to support new equipment
  • Installation of new pumps for circuit
  • Removal of screens pumps & associated redundant equipment